Concrete Slab with Footing Calculator

Concrete Slab with Footing Calculator

Estimate slab concrete, footing concrete, base gravel, vapor barrier, rebar grid, dowels, forms, control joints, and practical order quantities for slab-on-grade pours with footings.

Real Project Presets

📏Slab, Footing, and Reinforcement Inputs

Enter the extra footing depth below the slab, not total thickness.
Use for L-shapes, partial walls, strip footings, or grade beams.

Calculated Pour Summary

Concrete To Order
0
cubic yards with waste
Slab Concrete
0
slab volume only
Footing Concrete
0
continuous footing volume
Rebar Total
0
linear feet plus laps
Gravel Base
0
cubic yards compacted
Forms and Vapor
0
forms / barrier area

🧰Material and Specification Grid

27
Cubic feet per yd³
0.60
ft³ per 80 lb bag
2"
Common rebar cover
6 mil
Minimum vapor barrier
12 ft
Typical form board
40D
Common lap estimate
24"
Max light slab grid
1/4T
Saw joint depth guide

📚Reference Tables

Slab UseTypical ThicknessCommon ReinforcementControl Joint Spacing
Patio or walkway4 in / 100 mm#3 at 18 to 24 in or mesh8 to 10 ft
Garage or shed4 to 5 in / 100 to 125 mm#4 at 18 to 24 in10 to 12 ft
Workshop or light vehicle5 to 6 in / 125 to 150 mm#4 at 12 to 18 in10 to 12 ft
Heavy storage or equipment6 to 8 in / 150 to 200 mm#5 at 12 to 18 in12 to 15 ft
Footing RoleWidth RangeDepth RangeTypical Bars
Nonbearing thickened edge10 to 12 in8 to 12 in below slab2 #3 or #4
Light framed wall12 to 16 in10 to 12 in below slab2 to 4 #4
Garage or shop wall16 to 20 in12 to 16 in below slab4 #4 or #5
Frost or bearing footingPer local codeBelow frost depthEngineer specified
Rebar SizeDiameterWeightTypical Slab Use
#33/8 in / 10 mm0.376 lb/ftLight pads and patios
#41/2 in / 13 mm0.668 lb/ftMost garage slabs
#55/8 in / 16 mm1.043 lb/ftThicker slabs and beams
#63/4 in / 19 mm1.502 lb/ftGrade beams and heavy edges
Concrete SourceNominal YieldUse In CalculatorPractical Note
Ready-mix truck1 yd³ increments varyTruck count estimateRound order upward
80 lb bagAbout 0.60 ft³Bag equivalentLarge slabs need many bags
60 lb bagAbout 0.45 ft³Bag equivalentGood for small pads
25 kg bagAbout 0.012 m³Metric bag equivalentConfirm bag yield label

💡Placement Tips

Volume tip: footing trench walls are rarely perfect. Use the 10% or 12% overage setting when excavation is rough, soil sloughs into the trench, or the slab edge is hand-shaped.
Rebar tip: the grid estimate includes a simple lap allowance, but chair spacing, bends, corner bars, and code-required dowels can add material beyond straight-run totals.
Safety note: Concrete slabs and footings can be structural elements. Verify frost depth, soil bearing, reinforcement, anchor bolts, drainage, and inspection requirements with your local building authority or a qualified professional before pouring.

It’s easy enough to plug the numbers into the calculator at the top of the page. But knowing how it works will help you avoid some expensive mistake. When you work through the math, you’ll see that concrete isn’t simply level cement. A slab is a complex piece of engineering involving poured cement, steel, earth, gravel, and vapor barriers. Get your ratios wrong and you’re looking at structural failure. Or, you’ve just wasted two-hundred bucks on material that sets up in the back of a truck while you wait for another load.

The first thing most folks do is measure length and width of the slab. Then they choose a thickness… and stop. That’s usually wrong as it fails to consider the footing. A properly built slab-on-grade foundation feature a footing, a turned-down, thickened perimeter below the primary slab surface. This footing prevent frost heave and transfers the load to stable soil. Unless you factor the footing’s volume separately, you’ll come up short when ordering concrete.

How to Use the Concrete Calculator

The tool allows you to divide slab volume from footing volume, and visualize how all that extra material is required in the slab’s turned-down edges. It also lets you select whether to pour the footing separately (days prior), versus pouring edge and slab in a single continuous motion; known as a monolithic pour. Different reinforcement and formwork considerations apply depending on the foundation type, so knowing what kind of foundation you’re building should precede cubic-yard calculations.

Reinforcement, however, goes against our intuition. You might think more steel is always better, but spacing and size matter more then sheer volume. Rebar for a typical garage slab is #4 (half inch thick). They lay it out in a grid with one dimension matching the control joint spacing. So if they’re spaced too wide, then the concrete can still crack in-between them. But if they’re too close together, the aggregate stone can’t move freely past the steel while mixing, making it hard to get placed. The rebar calculator gives you the estimated total linear feet required by taking into account your desired grid spacing. It also adds some extra for laps. These are important because rebar doesn’t exist in fifty-foot pieces. Instead, it’s in forty or sixty foot pieces. And you need to overlap them to make sure they continue. But without taking into account lap length you could of easily be short just where you need it most: the corner of your shed.

But what about the concrete? While that gets most of the attention, so should the underlying material. That’s right: gravel. Gravel do all the heavy lifting by resisting settlement and hydrostatic pressure to provide stability for the slab. A four-inch compacted crushed stone base is standard for light loads, but heavier equipment requires more. For heavier loads such as offices or industrial buildings, go deeper. Our tool will calculate how many yards of gravel are required given the dimensions of an area and desired depth, useful if you have to order delivery trucks. If you don’t put down enough base there will be voids underneath the slab. If you put in too much, you will waste money and raise the slab higher then necessary.

The last variable between amateur and professional is waste factors. Forms aren’t perfect. Concrete trucks don’t carry an exact amount. Soil trenches slough in a little bit. Depending on how rough your excavation is, you can input up to 15 percent overage on the calculator. Ten percent is a safe bet for most residential projects. Better to have a half-yard left over for patches than to be short when the truck’s already halfway back to the plant. Order carefully. Pour with confidence and let the slab settle in place without surprise costs.